The plan was to begin working on the electrical today, laying out and planning everything, starting to pull wire in the afternoon. That would be blown, I knew, because I knew just how bad that leak in the winter had been, and I knew what the subfloor would look like.
Sure enough, that because evident Saturday during demolition day.
Another thing became evident: we would have to do something about the door to the deck. The header wasn’t much of a header. But when we chalked a line above the 2×8 that ran across the top of the windows, ostensibly supporting them, and saw a 3/8 inch difference between the middle edge and the corners, we realized we had more work to do.
So the subfloor work gets moved to Wednesday as we spend tomorrow fixing this huge issue.
And the electrical? Well, who knows?
On the upside, the cucumbers and blueberries are growing nicely, and the outdoor kitchen is functioning very well indeed.
0 Comments