matching tracksuits

fun in threes, sometimes fours

Hide and Seek

For two weeks, it’s been approaching: the moment when hours upon hours of work disappear under insulation and drywall. The LVL that serves as the header for both the window opening and door, the installation of which was a day-long extravaganza of sweating and straining, will be visible only in pictures.

VIV_5024

The runs of 12-gauge and 14-gauge wires, all the pretty yellow and white lines snaking through the walls, will disappear, and the only evidence will be a working, properly grounded wiring system — what most folks take for granted in the developed world.

VIV_5027

The gas line that pops up from the floor will be hidden behind our new stove, though the majority of it (along with the new floor-supporting beam) will always be invisible, hidden in the crawl space.

DSCF9679

All these things were running through my head as I lazily prepared to install the insulation, thus hiding everything we’d spent so much time and money creating over the last two weeks. It was a job the Boy, who loves to help with everything, could have easily done — no heavy lifting, nothing dangerous edges — except for the fact that we had no protective gear for his eyes and lungs. And even if we had, I would be reticent to let him help with such a job. The least physically demanding yet the most dangerous in a way.

VIV_5030

I put some music on — Led Zepplin’s 2012 Celebration Day live album — and got to covering up everything we’d done.

VIV_5031

Job done, I tore down the plastic separating the kitchen from the rest of the house — we’ll need to protect the rest of the house throughout the process, but this particular piece of plastic was hung on a 2×4 that would make drywalling impossible — and thought how weird it was to have unrestricted access once again.

VIV_5033

Nap

1-DSCF9675

Home Runs

This was supposed to be last Tuesday.

1-160621

Wires

(Obviously, not our actual kitchen...)

The wiring in our house was somewhat of a mystery. Why doesn't that three-way switch in the kitchen and hall work properly? Where does that line go? Where did that line come from?

Most of the morning was spent working out those details so we could kill a couple of breakers and start pulling out old wires. In their place, we placed some shiny new boxes for switches and outlets and pulled a bit of 14-gauge wire for a few of the outlets. It was another of those days where we accomplished a lot but it doesn't quite look that way.

Tomorrow, though, it all starts coming together. We'll finish the majority of the wiring, but since that involves significant time in the attic, we'll be starting quite early. The plan was originally to start at six, but since the weather report indicates a mild morning, I called and left a message that we could probably wait until seven to start. I know, however, that my mentor, like I, sometimes misses messages on his phone, so I'm not sure when we're actually starting, which is why I'm going to bed now.

Weekend at the Lake

Returning

You should always return borrowed items in better shape than you received them.

So the neighbor will receive his truck back a bit cleaner than he lent it and with a full tank of gas.

We're done with the truck, which means we've hauled away the last of the old kitchen. Today we unloaded drywall, wood panelling, rotten subfloor, tired brick molding, and bits and pieces we'd accumulated. The kitchen is stripped and repaired, ready for the new starting Monday with electrical and plumbing. Out with the old. In with the mystery.

Sub

Two things got accomplished today: we got the window back in, which took most of the morning, and we got the subfloor fixed, which took most of the afternoon.

The evening was for family.

Crawling Space

The light was particularly beautiful this morning given the fact that I knew we would be spending the whole day in the crawl space.

DSC_4291

It was a blessing and a curse, really. The heat outside was so oppressive that it was really almost pleasant in the crawl space, which made it a welcome change from yesterday. On the other hand, it’s the crawl space.

Out mission was simple: deal with a 3/4 inch sag in the dining room portion of the floor.

floor1

A seven-foot level showed the problem clearly. The idea behind the solution was simple: build two piers to hold a new support beam under the affected area. An easy idea with a back-breaking implementation.

DSC_4301

But the beam is up, and the jacks are still temporarily in place. “The floor will need to settle a little before we make any definitive moves,” my mentor/guide explained.

floor2

For now, things look good.

Support

01-DSC_4252

A header is meant to support the span of the door so that the weight of the house is not actually on the door but on the header above the door. What happens if you don't build the header correctly? You'll have weight bearing down on things that aren't designed to take weight.

02-DSC_4253

What happens if you don't build the header correctly and the door is on the corner of the house? You get a door that's almost impossible to open.

03-DSC_4254

What happens if you put a lot more weight on a floor than it's designed to handle and leave it there for a long time. You'll get a lot of sag. Approximately 5/8 to 3/4 inch in our case.

See that "header" above the door? All the weight was on those 2x4's nailed together, which in turn sit on two 2x4's below them. That's why the door wouldn't open.

04-DSC_4256

Apparently, the holding mess that was in the house a couple of owners ago was concentrated in the dining area, which is why the floor sags there.

These two "whichs" are why my mentor said, "Well, we're putting off electrical for a few more days so we can fix the structural issues."

05-DSC_4260

So with the help of a third man, we built a temporary wall to support the structure while we knocked out the "header." Then we jacked up the roof and installed two LVL beams to make a new header for the entire door/window section, making sure that the supports for the beams rested on the columns below in the crawl space.

And by then, it was time to quit. So we boarded up the gaping hole, hung plastic to protect it all from rainfall, cleaned up, and called it a day.

Well, the other two gentlemen called it a day (at least for this project). I continued by clearing the floor of any debris and marking the floor, with the help of a six-foot level, for the areas where it sags.

Tomorrow we get to do it all again, except in the crawl space, without the ridiculously heavy LVL beams.

I'd like to find out who the "contractor" is that put this together and send photos of this "work" to every building inspector in the county along with his name. "You might want to check his work carefully."

08-DSC_4273

More Invisible Progress

The plan was to begin working on the electrical today, laying out and planning everything, starting to pull wire in the afternoon. That would be blown, I knew, because I knew just how bad that leak in the winter had been, and I knew what the subfloor would look like.

Sure enough, that because evident Saturday during demolition day.

Another thing became evident: we would have to do something about the door to the deck. The header wasn't much of a header. But when we chalked a line above the 2x8 that ran across the top of the windows, ostensibly supporting them, and saw a 3/8 inch difference between the middle edge and the corners, we realized we had more work to do.

So the subfloor work gets moved to Wednesday as we spend tomorrow fixing this huge issue.

And the electrical? Well, who knows?

On the upside, the cucumbers and blueberries are growing nicely, and the outdoor kitchen is functioning very well indeed.